We reported before on the City of Port Phillip’s Integrated Transport Strategy. Impressively, it includes plans for 14 new separated, protected bike routes.
Port Phillip BUG met with the Mayor, Dick Gross, in February, to find out when these are going to happen.
Route 1 Moray St has already been implemented by the Melbourne Metro Project.
Route 2 Albert Rd— Kerferd Rd has been taken over by the State Government, in the form of the Shrine to Sea project. It’s being administered by Parks Victoria. We’ve participated in a consultation about this, but we’re not really sure what is going to happen and when.
Routes 3 and 6 are to be completed by 2021-2022. Route 3 is the Park St Link. We don’t know if any planning has started on this yet. Route 6 is Inkerman St. There are some plans for very minor upgrades at some intersections (not much more than green paint).
Planning has started on route 4 (Garden City link to Sandridge trail) but all that is publicly available so far are plans for a minor upgrade to the shared path.
Routes 1—13 are to be completed by 2028, with the remainder completed after that.
We will continue to monitor progress— even the best plans are useless if they’re not implemented!